Effects of non-performance within a specified time, in a contract in which time is essential
Original source · 2026-09-17
▶Show summaryHide summary
In brief
When you enter into a contract, the agreement often specifies that certain actions must be completed by a specific deadline. If one party fails to perform their obligations on time, disputes can arise regarding whether the contract can be cancelled or if compensation is owed.
What the law establishes
Under Cyprus law, the consequences of missing a contract deadline depend on whether the parties intended for time to be an essential part of the agreement (often referred to as "time being of the essence"):
- When time is essential: If the parties intended for the deadline to be a critical term of the contract, any failure to perform on time makes the contract (or the uncompleted part of it) "voidable" at the option of the receiving party. This means the party waiting for performance has the legal right to choose whether to cancel the contract.
- When time is not essential: If the deadline was not intended to be a critical term, the contract cannot be cancelled just because of the delay. However, the receiving party is still entitled to claim compensation from the delaying party for any financial loss or damage caused by the delay.
- Accepting late performance: If the contract was eligible for cancellation due to a missed critical deadline, but the receiving party decides to accept late performance anyway, they lose their right to claim compensation for the delay. The only way to preserve the right to claim damages is to explicitly notify the delaying party of this intention at the exact time of accepting the late performance.
In practice
- Be clear about deadlines: When drafting a contract, explicitly state whether deadlines are critical ("time is of the essence"). If a deadline is vital to your business or personal plans, the contract should clearly reflect this intention.
- Know your options if there is a delay: If the other party misses a critical deadline, you must decide whether to cancel the contract or allow them to finish late.
- Speak up when accepting late work: If you choose to accept late performance but still want to claim compensation for the delay, you must formally notify the other party of your intention to claim damages at the very moment you accept their late work. If you accept it silently, you waive your right to compensation.
▶Show full textHide full text
1. If one of the contracting parties undertook the obligation to perform a certain act within a specified time or before that time, or certain acts within specified times or before those times, and fails to perform any such act at or before the specified time, the contract or the part of the contract that has not yet been performed becomes voidable at the option of the creditor, if the intention of the contracting parties was to make time an essential term of the contract.
2. If the intention of the contracting parties was not to make time an essential term of the contract, the contract does not become voidable by reason of the debtor's failure to act within or before the specified time; however, the creditor is entitled to compensation from the debtor for any damage which he may have suffered by reason of such failure.
3. In the case of a voidable contract due to the debtor's failure to perform his promise at the time agreed, if the creditor accepts performance of the promise at a time other than that agreed, then he cannot claim compensation for any damage suffered due to non-performance at the time agreed, unless, at the time of acceptance, he gives notice to the debtor of his intention to claim compensation.
▶Original (Greek)Hide original
1. Αν ένας από τους συμβαλλόμενους ανέλαβε την υποχρέωση να προβεί σε ορισμένη ενέργεια εντός ορισμένου χρόνου ή πριν από το χρόνο αυτό, ή σε ορισμένες ενέργειες εντός ορισμένων χρόνων ή πριν από τους χρόνους αυτούς, και παραλείψει να προβεί σε οποιαδήποτε τέτοια ενέργεια κατά ή πριν από τον ορισμένο χρόνο, η σύμβαση ή το μέρος της σύμβασης που δεν εκπληρώθηκε ακόμη καθίσταται ακυρώσιμο κατ’ εκλογή του δανειστή, αν πρόθεση των συμβαλλόμενων ήταν να καταστήσουν το χρόνο ουσιώδη όρο της σύμβασης.
2. Αν πρόθεση των συμβαλλόμενων δεν ήταν να καταστήσουν το χρόνο ουσιώδη όρο της σύμβασης, η σύμβαση δεν καθίσταται ακυρώσιμη λόγω παράλειψης του οφειλέτη να ενεργήσει εντός του ορισμένου χρόνου ή πριν από αυτόν~ ο δανειστής όμως έχει δικαίωμα αποζημίωσης από τον οφειλέτη για κάθε ζημιά, την οποία ήθελε υποστεί λόγω της παράλειψης αυτής.
3. Σε περίπτωση ακυρώσιμης σύμβασης λόγω παράλειψης του οφειλέτη να εκπληρώσει την υπόσχεση του στο χρόνο που συμφωνήθηκε, αν ο δανειστής αποδεχτεί εκπλήρωση της υπόσχεσης σε χρόνο άλλον από αυτόν που συμφωνήθηκε, τότε δεν δύναται να αξιώσει αποζημίωση για ζημιά που υπέστη λόγω μη εκπλήρωσης κατά το χρόνο που συμφωνήθηκε, εκτός αν, κατά το χρόνο της αποδοχής, γνωστοποιήσει στον οφειλέτη την πρόθεση του να αξιώσει αποζημίωση.
This information is for general guidance only and is not legal advice. Check the primary source and consult a lawyer where necessary.